01 NCAC 30E .0303          POST OCCUPANCY EVALUATION

The designer evaluation process allows for a second evaluation to be conducted within 36 months of the completion of a capital project if design‑related latent defects are discovered. A separate procedure of the State Building Commission may require a formal post‑occupancy evaluation within 12 months of a building completion. The data from the 12 month post‑occupancy evaluation can be used as a substitute for the follow‑up designer evaluation if the Capital Projects Coordinator so determines.

 

History Note:        Authority G.S. 143‑135.25; 143‑135.26;

Eff. October 1, 1988;

Pursuant to G.S. 150B-21.3A, rule is necessary without substantive public interest Eff. July 22, 2018.